Sl. No Case No. Date Matter
121. OA-362/20-21 Tuesday, April 12, 2022 APPLICATION FOR REMOVAL OF DIFFICULTIES IN ACHIEVING THE NORMATIVE STATION HEAT RATE ALLOWED BY THE HON'BLE COMMISSION FOR SAGARDIGHI THERMAL POWER PROJECT, STAGE-II OF 1000 MW (2 X 500 MW) CAPACITY IN TERM OF REGULATION 8.10 OF THE WEST BENGAL ELECTRICITY REGULATORY COMMISSION ( TERMS AND CONDITIONS OF TARIFF) REGULATIONS, 2011 AS AMENDED FROM TIME TO TIME.
122. OA-389/21-22 Monday, April 11, 2022 IN REGARD TO THE APPLICATION SUBMITTED BY WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LIMITED (WBSEDCL) FOR ISSUANCE OF APPROPRIATE ORDER IN RESPECT OF REMOVAL OF DIFFICULTIES, FOR IMPLEMENTING MECHANISM OF CONSUMER'S PAYMENT AND LATE PAYMENT SURCHARGE (LPSC) ADJUSTMENT, AS PER REGULATION 8.10 OF WEST BENGAL ELECTRICITY REGULATORY COMMISSION ( TERMS AND CONDITIONS OF TARIFF) REGULATIONS, AS AMENDED FROM TIME TO TIME
123. C-15/993 Wednesday, February 23, 2022 IN THE MATTER OF APPLICATIONS BY SURYA ALLOY INDUSTRIES LIMITED, SEEKING INTERVENTION OF THE COMMISSION IN THE MATTER OF ARBITRARY AND UNJUSTIFIED DEMAND ON ACCOUNT OF ADDITIONAL ENERGY CHARGES DURING RESTRICTED DRAWAL PERIOD FOR THE MONTHS BETWEEN JUNE 2015 TO JULY,2018.
124. OA-341/20-21 Saturday, February 12, 2022 IN THE MATTER OF APPLICATION UNDER SECTION 86(1)(f) READ WITH SECTION 86(1)(a) OF THE ELECTRICITY ACT,2003 FOR ADJUDICATION OF DISPUTES BETWEEN PHILIPS CARBON BLACK LIMITED [PCBL (PETITIONER)] AND WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LIMITED [WBSEDCL (RESPONDENT NO.1)] AND WEST BENGAL STATE ELECTRICITY TRANSMISSION COMPANY LIMITED [WBSETCL (RESPONDENT NO.2)] IN REGARD TO DETERMINATION/ADOPTION OF CHARGES PAYABLE BY THE PETITIONER TO THE RESPONDENT NO.1,IF ANY,FOR CONVEYANCE OF SURPLUS POWER FROM PETITIONER'S CO-GENERATION PLANT THROUGH OPEN ACCESS PURSUANT TO THE RESTRUCTURING OF ERSTWHILE DURGAPUR PROJECTS LIMITED(DPL).
125. OA-261/17-18 Saturday, February 12, 2022 IN REGARD TO THE APPLICATION SUBMITTED BY THE WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LIMITED (WBSEDCL) FOR ISSUANCE OF APPROPRIATE ORDER DETERMINING DIFFERENT CHARGES TO RECOVER FROM OPEN ACCESS CUSTOMERS IN TERMS OF REGULATION 27 OF THE WEST BENGAL ELECTRICITY REGULATORY COMMISSION ( OPEN ACCESS) REGULATIONS, 2007 AS AMENDED FOR REMOVAL OF DIFFICULTIES TO MEET THE POWER REQUIREMENT OF THE OPEN ACCESS CUSTOMERS BY DISTRIBUTION LICENSEE
126. OA-348/20-21 Wednesday, February 9, 2022 IN REGARD TO THE APPLICATION SUBMITTED BY THE WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LIMITED (WBSEDCL) FOR INVESTMENT APPROVAL FOR CONVERSION OF OVERHEAD DISTRIBUTION SYSTEM TO UNDERGROUND AT CHINSURAH AND KRISHNANAGAR TOWN IN HOOGHLY AND NADIA DISTRICT RESPECTIVELY IN TERMS OF REGULATION 2.8.2.3 OF THE WEST BENGAL ELECTRICITY REGULATORY COMMISSION ( TERMS AND CONDITIONS OF TARIFF) REGULATIONS, 2011, AS AMENDED
127. OA-386/21-22 Thursday, February 3, 2022 IN REGARD TO THE APPLICATION FOR ISSUANCE OF APPROPRIATE ORDER FOR UNIVERSALIZATION OF MONTHLY BILLING CYCLE OR BILLING PERIOD FOR ALL CONSUMERS OF WBSEDCL
128. OA-372/20-21 Wednesday, February 2, 2022 IN REGARD TO THE APPLICATION SUBMITTED FOR IN-PRINCIPLE CLEARANCE FOR INSTALLATION OF FLUE GAS DESULPHURIZATION (FGD) IN THE 3 X 150 MW THERMAL POWER STATION OF HIRANMAYE ENERGY LIMITED
129. OA-373/21-22 Monday, January 31, 2022 IN REGARD TO THE APPLICATION SUBMITTED BY THE WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LIMITED (WBSEDCL) FOR INVESTMENT APPROVAL FOR DISTRIBUTION SYSTEM IMPROVEMENT SCHEME (DSIS) IN TERMS OF REGULATION 2.8.2.3 OF THE WEST BENGAL ELECTRICITY REGULATORY COMMISSION ( TERMS AND CONDITIONS OF TARIFF) REGULATIONS, 2011, AS AMENDED
130. B-11/23 Monday, January 24, 2022 IN REGARD TO IMPLEMENTATION OF THE DIRECTIONS OF THE GOVERNMENT OF WEST BENGAL IN THE DEPARTMENT OF POWER DATED 23.12.2021 UNDER SECTION 108 OF THE ELECTRICITY ACT,2003 TO THE WEST BENGAL ELECTRICITY REGULATORY COMMISSION TO ISSUE APPROPRIATE ORDER FOR PROVIDING SUBSIDY TO THE CONSUMERS IN REGARD TO THE TARIFF ORDER DATED 25.08.2021 PASSED BY THE COMMISSION IN RESPECT OF WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LIMITED
131. C-15/993 Friday, January 21, 2022 IN THE MATTER OF APPLICATIONS BY SURYA ALLOY INDUSTRIES LIMITED, SEEKING INTERVENTION OF THE COMMISSION IN THE MATTER OF ARBITRARY AND UNJUSTIFIED DEMAND ON ACCOUNT OF ADDITIONAL ENERGY CHARGES DURING RESTRICTED DRAWAL PERIOD FOR THE MONTHS BETWEEN JUNE 2015 TO JULY,2018.
132. OA-339/20-21 Thursday, January 20, 2022 IN REGARD TO THE APPLICATION SUBMITTED BY CESC LIMITED FOR IN-PRINCIPLE APPROVAL OF CAPITAL EXPENDITURE FOR INSTALLATION OF LIMESTONE BASED WET FLUE GAS DESULPHURIZATION PLANT AT BUDGE BUDGE GENERATING STATION
133. OA-338/20-21 Thursday, January 20, 2022 IN REGARD TO THE APPLICATION SUBMITTED BY HALDIA ENERGY LIMITED (HEL) FOR IN-PRINCIPLE APPROVAL OF CAPITAL EXPENDITURE FOR INSTALLATION OF LIMESTONE BASED WET FLUE GAS DESULPHURIZATION PLANT FOR 2 x 300 MW COAL BASED THERMAL PROJECT AT HALDIA
134. OA-381/21-22 Monday, January 3, 2022 IN REGARD TO THE APPLICATION SUBMITTED BY THE WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LIMITED (WBSEDCL) FOR ISSUANCE OF APPROPRIATE ORDER FOR IMPLEMENTING DEMAND CHARGE TO ALL CLASS OF CONSUMERS HAVING CONTRACT LOAD OF 30 KVA AND ABOVE UNDER MONTHLY BILLING SYSTEM AT A RATE AS STIPULATED IN THE RESPECTIVE TARIFF ORDER FOLLOWING THE REGULATION 4.3.1 OF WEST BENGAL ELECTRICITY REGULATORY COMMISSION (TERMS AND CONDITIONS OF TARIFF) REGULATIONS, 2011, AS AMENDED
135. OA-340/20-21 Monday, December 27, 2021 IN THE MATTER OF APPLICATION MADE BY THE WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LIMITED (WBSEDCL) FOR ISSUANCE OF APPROPRIATE ORDER UNDER REGULATION 2.1.3. (C) OF THE WEST BENGAL ELECTRICITY REGULATORY COMMISSION ( CONDUCT OF BUSINESS), 2013 AS AMENDED SO THAT CONSUMERS OF WBSEDCL DOES NOT REQUIRE TO BEAR HIGH ENERGY COST OF THERMAL POWER STATION AT RAGHUNATHPUR, PURULIA DISTRICT, WEST BENGAL (RTPS) OF DAMODAR VALLEY CORPORATION (DVC)
136. OA-382/21-22 Wednesday, December 22, 2021 IN REGARD TO THE APPLICATION SUBMITTED BY INDIA POWER CORPORATION LIMITED (IPCL) UNDER REGULATION NO. 5.15.1 OF THE WEST BENGAL ELECTRICITY REGULATORY COMMISSION ( LICENSING AND CONDITIONS OF LICENSE) REGULATIONS, 2013 SEEKING INTERPRETATION WITH RESPECT TO LICENSE AND TERMS AND CONDITIONS OF LICENSE OF IPCL
137. OA-349/20-21 Thursday, December 16, 2021 IN THE MATTER OF APPLICATION BY ULTRATECH CEMENT LIMITED SEEKING INTERVENTION OF THE COMMISSION IN REGARD TO RELEASE OF NOC BY WBSEDCL FOR WHEELING OF 7.425 MW AND 10.00 MW OF POWER BY ULTRATECH CEMENT LIMITED FROM THEIR CAPTIVE POWER PLANT AT BHATAPARA - BALODA BAZAR , CHHATTISGARH TO THEIR WORKS AT DANKUNI, WEST BENGAL AND RAGHUNATHGANJ, DISTRICT: MURSHIDABAD, WEST BENGAL, RESPECTIVELY
138. OA-377/21-22 Friday, December 10, 2021 IN REGARD TO THE APPLICATION SUBMITTED BY INDIA POWER CORPORATION LIMITED FOR APPROVAL OF DETAILED PROCEDURE FOR RECEIVING AND DISPOSAL OF APPLICATION FOR CONNECTIVITY OF SOLAR PV GENERATING SYSTEM OF ELIGIBLE CONSUMERS AS REQUIRED UNDER REGULATION 16.9 OF THE WEST BENGAL ELECTRICITY REGULATORY COMMISSION (COGENERATION AND GENERATION OF ELECTRICITY FROM RENEWABLE SOURCES OF ENERGY) (FIRST AMENDMENT) REGULATIONS, 2020
139. OA-351/20-21 Wednesday, December 8, 2021 APPLICATION BY BRAITHWAITE & COMPANY LIMITED SEEKING DIRECTION BY THE COMMISSION UPON CESC LIMITED TO ALLOW NET METERING FOR ROOF TOP GRID CONNECTED SOLAR PLANT UNDER RESCO MODEL AND ADJUDICATION OR RESOLUTION OF DISPUTE REGARDING REGULATION OF PURCHASE AND PROCUREMENT PROCESS OF ELECTRICITY
140. OA-367/21-22 Wednesday, December 1, 2021 IN REGARD TO THE APPLICATION SUBMITTED BY THE WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LIMITED (WBSEDCL) FOR APPROVAL OF THE CONNECTION PROCEDURES FOR SOLAR PV GENERATING SYSTEM UNDER NET METERING OR NET BILLING ARRANGEMENT UNDER WBSEDCL PROCEDURE-C(2021) IN TERMS OF REGULATION 16.9 OF THE WEST BENGAL ELECTRICITY REGULATORY COMMISSION (COGENERATION AND GENERATION OF ELECTRICITY FROM RENEWABLE SOURCES OF ENERGY) REGULATIONS,2013, AS AMENDED
141. OA-376/21-22 Monday, November 29, 2021 IN REGARD TO THE APPLICATION SUBMITTED BY CESC LIMITED FOR APPROVAL OF PROCEDURE FOR EFFECTING CONNECTIVITY OF SOLAR PV GENERATING SYSTEM (SPGS) OF ELIGIBLE CONSUMERS WITH THE DISTRIBUTION NETWORK OF CESC LIMITED IN TERMS OF REGULATION 16.9 OF THE WEST BENGAL ELECTRICITY REGULATORY COMMISSION (COGENERATION AND GENERATION OF ELECTRICITY FROM RENEWABLE SOURCES OF ENERGY) REGULATIONS,2013, AS AMENDED
142. OA-235/16-17 Friday, November 12, 2021 IN REGARD TO THE APPLICATION SUBMITTED BY THE WEST BENGAL POWER DEVELOPMENT CORPORATION LIMITED (WBPDCL) FOR IN-PRINCIPLE APPROVAL FOR INVESTMENT IN RENOVATION AND MODERNIZATION PROGRAMME IN RESPECT OF UNITS 1,2, AND 3 OF KOLAGHAT THERMAL POWER STATION IN TERMS OF REGULATION 2.8.4.2.1 OF THE WEST BENGAL ELECTRICITY REGULATORY COMMISSION (TERMS AND CONDITIONS OF TARIFF) REGULATIONS,2011, AS AMENDED
143. OA-366/21-22 Tuesday, November 2, 2021 IN REGARD TO THE APPLICATION SUBMITTED BY THE WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LIMITED (WBSEDCL) FOR INVESTMENT APROVAL OF 'SECOND PHASE WORK' UNDER THE SCHEME FOR DISTRIBUTION NETWORK STRENGTHENING AND GRID MODERNIZATION IN TERMS OF REGULATION 2.8.2.3 OF THE WES BENGAL ELECTRICITY REGULATORY COMMISSION (TERMS AND CONDITIONS OF TARIFF) REGULATIONS,2011, AS AMENDED
144. OA-346/20-21 Tuesday, November 2, 2021 IN REGARD TO THE APPLICATION SUBMITTED BY THE WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LIMITED (WBSEDCL) FOR INVESTMENT APPROVAL OF 'FIRST PHASE WORK' UNDER THE SCHEME FOR DISTRIBUTION NETWORK STRENGTHENING AND GRID MODERNIZATION IN TERMS OF REGULATION 2.8.2.3 OF THE WEST BENGAL ELECTRICITY REGULATORY COMMISSION (TERMS AND CONDITIONS OF TARIFF) REGULATIONS, 2011, AS AMENDED
145. OA-362/20-21 Saturday, October 30, 2021 IN THE MATTER OF APPLICATION FOR REMOVAL OF DIFFICULTIES IN ACHIEVING THE NORMATIVE STATION HEAT RATE ALLOWED BY THE HON'BLE COMMISSION FOR SAGARDIGHI THERMAL POWER PROJECT,STAGE-II OF 1000 MW (2x500 MW) CAPACITY IN TERM OF REGULATION 8.10 OF THE WEST BENGAL ELECTRICITY REGULATORY COMMISSION (TERMS AND CONDITIONS OF TARIFF) REGULATIONS,2011 AS AMENDED TIME TO TIME
146. OA-341/20-21 Friday, October 29, 2021 IN THE MATTER OF APPLICATION UNDER SECTION 86(1)(f) READ WITH SECTION 86(1)(a) OF THE ELECTRICITY ACT,2003 FOR ADJUDICATION OF DISPUTES BETWEEN PHILIPS CARBON BLACK LIMITED [PCBL (PETITIONER)] AND WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LIMITED [WBSEDCL (RESPONDENT NO.1)] AND WEST BENGAL STATE ELECTRICITY TRANSMISSION COMPANY LIMITED [WBSETCL (RESPONDENT NO.2)] IN REGARD TO DETERMINATION/ADOPTION OF CHARGES PAYABLE BY THE PETITIONER TO THE RESPONDENT NO.1,IF ANY,FOR CONVEYANCE OF SURPLUS POWER FROM PETITIONER'S CO-GENERATION PLANT THROUGH OPEN ACCESS PURSUANT TO THE RESTRUCTURING OF ERSTWHILE DURGAPUR PROJECTS LIMITED(DPL).
147. OA-355/20-21 Tuesday, October 26, 2021 IN THE MATTER OF PETITION FOR CONSIDERATION OF NET METERING FOR 3 MW ROOF TOP SOLAR PV TO BE DEVELOPED BY BHARAT ELECTRONICS LIMITED (BEL) IN THE PREMISES OF METAL & STEEL FACTORY (MSF) AT ISHAPORE
148. WBERC/A-82/2 Monday, October 25, 2021 IN REGARD TO THE ORDER OF THE WEST BENGAL ELECTRICITY REGULATORY COMMISSION TO REMOVE THE DIFFICULTY FACED BY THE INTENDING CONSUMERS FALLING UNDER NET BILLING AS PER PROVISIONS OF THE WEST BENGAL ELECTRICITY REGULATORY COMMISSION (CO-GENERATION AND GENERATION OF ELECTRICITY FROM RENEWABLE SOURCES OF ENERGY) REGULATIONS,2013, AS AMENDED
149. OA-319/19-20 Tuesday, October 5, 2021 IN REGARD TO THE APPLICATION SUBMITTED BY THE WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LIMITED (WBSEDCL) FOR INVESTMENT APPROVAL OF CIVIL PROJECT WORKS BY WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LIMITED (WBSEDCL) IN TERMS OF REGULATION 2.8.2.3 OF THE WEST BENGAL ELECTRICITY REGULATORY COMMISSION (TERMS AND CONDITIONS OF TARIFF) REGULATIONS,2011, AS AMENDED
150. OA-371/21-22 Wednesday, September 29, 2021 IN REGARD TO THE APPLICATION SUBMITTED BY THE WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LIMITED (WBSEDCL) FOR ISSUANCE OF APPROPRIATE ORDER ALLOWING PROPORTIONATE POWER PURCHASE COST INCLUDING ALLIED TRANSMISSION CHARGE FOR SURPLUS POWER SOLD TO THE PERSONS OTHER THAN ITS OWN CONSUMERS AND LICENSEES DURING FUEL AND POWER PURCHASE COST ADJUSTMENT (FPPCA) ORDER IN ORDER TO PASS ON BENEFIT OF PARTLY RECOVERED FIXED COST TO CONSUMERS FROM ABOVE SALE OF SURPLUS POWER DURING TRUE UP